3Ts Hospital Redevelopment

Timeline

The dated listed below are subject to the timing of various stages of Department of Health and HM Treasury approval: 

  • Autumn 2012
    Winter protection work begins on St Mary's Hall.

  • Winter 2012/13
    Preparation of temporary buildings and the air ambulance landing pad begins.

  • Autumn 2013
    Services and staff affected by the construction of Stage 1 begin the move to alternative locations.

  • Autumn 2014
    Services and staff moves are completed. Construction of Stage 1 begins.

  • Summer 2018  
    Stage 1 is completed and ready for use. Services move into Stage 1.

  • Summer 2018
    Construction on Stage 2 begins.

  • Autumn 2021
    Stage 2 is completed.

  • Winter 2022
    New service yard and entire redevelopment complete.